Point-to-point wireless links: connecting buildings with microwave and millimetre-wave bridges

In short: A point-to-point wireless link connects two buildings or sites without digging trenches for fibre. Links use unlicensed bands such as 5 and 60 GHz or licensed microwave and E-band. They need clear line of sight, including the Fresnel zone around the direct path, a link budget with enough margin, and solid mounting. Higher frequencies give more capacity but shorter range and more rain fade.

When to use a wireless bridge

Laying fibre between buildings can take months and cost a lot when it crosses roads, rivers or land you do not own. A wireless bridge can be installed in a day. Common uses: connecting a school's separate buildings, a warehouse across a car park, a temporary site, CCTV on a far fence, or a backup path alongside fibre. Mobile operators use the same technology for backhaul.

Planning a wireless bridge between buildingsLine of sightand FresnelzoneFrequency5, 6, 60 or 80GHzLink budgetdistance,antennasMountingstable,alignedBackupfibre orsecond link
Figure 1. A clear path is everything: trees, buildings and even the ground can block or weaken the link.

Frequency choices

BandLicenceTypical capacityTypical range
5 GHz / 6 GHzUnlicensed100 Mbps to 1+ GbpsSeveral km, crowded in cities
60 GHz (V-band)Unlicensed1 to 10 GbpsUp to about 0.5 to 1 km, oxygen absorption
6 to 42 GHz microwaveLicensed100 Mbps to 2+ GbpsSeveral to tens of km
70/80 GHz (E-band)Light licence1 to 20 GbpsUp to a few km, rain sensitive

Unlicensed bands are cheap and quick but can suffer interference. Licensed bands give you protected spectrum, worth it for important or long links. Rules and fees vary by country.

Line of sight and the Fresnel zone

The two antennas must see each other, but that is not enough. Radio energy travels in an ellipse-shaped region around the direct line, called the Fresnel zone, which is widest at the middle of the path. At least 60 percent of the first Fresnel zone should be clear of trees, buildings and terrain. For long links, mount antennas high enough and remember that trees grow and new buildings appear.

Link budget

Received signal = transmit power + antenna gains - path loss - other losses. The radio needs a minimum signal for each data rate. The difference between the expected signal and that minimum is the fade margin, which absorbs rain, fog and slight misalignment. Vendor planning tools calculate this, including expected availability for your location's rainfall. Above about 10 GHz, rain fade matters; E-band links may drop to lower speeds in heavy rain, and adaptive modulation keeps the link up at a lower rate.

Installation

  • Mount on rigid poles or walls; wind movement misaligns narrow beams, especially at high frequencies.
  • Align carefully using the radio's signal meter.
  • Protect with lightning arrestors and proper earthing; use outdoor-rated, shielded cables.
  • Encrypt the link (AES on the radio, or MACsec/IPsec on top).

Redundancy

A single wireless link can be affected by weather, interference or physical damage. For important connections, pair it with fibre (each as backup for the other), or use two links on different bands, such as E-band with a 5 GHz backup that keeps working in heavy rain at lower speed.

Real-world example: the sports hall

A school's new sports hall was 300 metres away across a public road, and a fibre trench would have taken eight months of permits. The school installed a 60 GHz bridge giving about 1 Gbps, with a 5 GHz link as backup. The hall had full network access, Wi-Fi and CCTV within a week of opening.

Practice

What is the Fresnel zone?
The ellipse-shaped region around the direct line between antennas that must be mostly clear (at least 60 percent of the first zone) for a strong link.
Why do E-band links lose speed in heavy rain?
At high frequencies, rain absorbs and scatters the signal (rain fade), so adaptive modulation lowers the data rate.
What is fade margin?
The extra signal above the minimum needed, which absorbs weather effects and misalignment.

Key takeaways

  • Wireless bridges connect buildings quickly where fibre is hard to lay.
  • Choose bands by capacity, range, interference and licensing.
  • Keep line of sight and the Fresnel zone clear; plan a link budget with fade margin.
  • Mount rigidly, encrypt, protect from lightning and add a backup path.
Tracks your learning on this device only. See your progress on the learning paths.
Verified author✓ Valid
Issued to
Mohamed Fayas
Role
Founder of FM TecHub
Credentials
CCNABTEC HND Network EngineeringBEng (Hons) Computer Networking & Cloud Security
Issuer
FM TecHub · fmtechub.com

He writes practical, plain-English guides on networking, security and cloud.

More about the author →

Original content written by Mohamed Fayas for FM TecHub. © 2026 FM TecHub. You're welcome to share a link to this page; please don't copy the text elsewhere without permission.

Email updates: coming soon

New notes, tools and security news from FM TecHub by email, explained simply. Free. We're not collecting email addresses yet; see our privacy policy.

PortServiceStatus
SMTP/25Email updatesopening soon

Meanwhile, stay connected: